Cap Project Update: 9/20/25

Dear MACS Family and Community,
As we continue progressing through our 2023 Capital Project, I want to take a moment to share some updates and express our appreciation for your ongoing support.
Over the past week, you may have noticed that a few contractors have completed their work in certain buildings and have begun clearing out. Teams are currently addressing final “punch list” items—those smaller details that ensure everything meets our standards and is fully operational.
At the same time, other parts of the project remain active, with crews continuing work on key areas that are still under development. Below, you’ll find a summary of what was accomplished last week and a look ahead at the next steps in our journey to enhance our school facilities.
Thank you for your patience and partnership as we work to create the best possible learning environment for our students.
Sincerely,
Dr. Runner, Superintendent
2023 Capital Improvement Project: Updates 9/20/25
Mexico High School
- Electrical wiring of the garage door sensor and running wiring and conduit for the exterior sign.
- Masonry grinding and repointing at High School
Mexico Middle School
- Final prepping of the stone for the lower driveway and parking lot
- Grading of the detention pond
- Starting to final grade at the disturbed areas
- Electrical wires for the front lift gate were ran from the front gate to the office.
- Basketball arms were installed.
- Running of the wiring and conduit for the lockdown/ lockout system continued.
Mexico Elementary
- Final installation of the lockdown/ lockout system
Palermo Elementary School
- Final installation of the lockdown/ lockout system
- Finished laying brick over the lintel
New Haven Elementary School
- Brick repointing and repair continued in the in courtyard
- Brick cleaning was performed
Next Steps
Middle School
- Rear Parking lot binder and top coat
- Stormwater detention pond corrections
- Site Stairs and railings
- Landscaping
- Gate operator arms
- Signage
- Benches, Basketball hoops
- Window Replacement
- Security devices
- High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Area M roofing flashing and coping
- Area L roof counter flashing
- LED Digital Display Sign
- Security devices
Mexico Elementary
- Masonry Restoration
- LED Digital Display Sign
- Window Replacements
New Haven Elementary
- Window Replacements
- LED Digital Display Sign
- Clocks
Palermo Elementary
- Masonry Restoration
- Window Replacements
- LED Digital Display Sign
- Clocks