September 5, 2025
Cap Project Update: 9/5/25
Dear MACS Family and Community,
We continue to make progress on the construction projects. Both the High School and Mexico Elementary roof replacements are complete. Roof replacement takes place in sections depending on prior replacement and warranty expirations. Contractors are finalizing paving at the Middle School and will be replacing landscaping soon. Capital Projects are always in the works so that we can maintain our facilities! Dr. Runner
Mexico High School
- Roof detailing on roof M
- Masonry grinding and repointing at High School
Mexico Middle School
- Final blacktop finish coat was installed
- Asphalt striping was done at the bus loop, parent drop off and teacher parking lot.
- Additional coat of concrete sealer is being installed to the concrete sidewalks.
- Gate lift pedestals were installed
- Topsoil is being placed
Mexico Elementary
- Moved (2) camera’s slightly in order to do the masonry repair.
- Installing Lockdown/ lockout buttons.
Palermo Elementary School
- Installation of brick at lintels
New Haven Elementary
- Installed the expansion joint on the front wall repair
- Brick repointing and repair continued in the in courtyard
Bus Garage
- Garage door openings, Handrailing and stairs were painted
Next Steps
- Middle School
- Rear Parking lot grading and stone base
- Stormwater detention pond corrections
- Site Stairs and railings
- Landscaping
- Gate operator
- Signage
- Benches, Basketball hoops
- High School
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Area M roofing flashing and coping
- Area L roof counter flashing
- Mexico Elementary
- Masonry Restoration
- LED Digital Display Sign
- Window Replacements
- New Haven Elementary
- Masonry Restoration
- Window Replacements
- Palermo Elementary
- Masonry Restoration
- Window Replacements