June 25, 2025
Cap Project Update: 6/20/25
2024/25 Capital Outlay Exception Project
Mexico Middle School
- Installation of the Nurse’s Office Cabinet
- Installation of the Nurse’s Office Window Sills
2023 Capital Improvement Project
Mexico High School
- Started extending the Catwalks in the Attic to accept the new AHU units
- Removal of the Condensate Tank
- Installation of the new Condensate Tank
- Masonry Mockup
Mexico Middle School
- Boxing out the area for the lower parking area on the Parent Drop off Triangle
- Installing the stone subbase in the upper parent drop off area.
- Install the stone subbase in the lower parking area of the parent drop off.
- Masonry Mockup
- Tested the water shut off in the building to make sure it worked properly for the water line change over
Mexico Elementary School
- Masonry Cleaning
Palermo Elementary School
- No work this week
New Haven Elementary School
- No Work this week
Next Steps
- 2023 Capital Improvement Project
- Middle School
- Parent drop off site work to continue
- Rough Grading and storm structure installation
- Rear parking lot demolition and storm retention structures
- Waterline Service/RPZ installation
- Middle School
- High School
- Extending the Catwalks in the Attic.
- New Roof Hatch installation
- Condensate Tank replacement
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- Mexico Elementary
- Masonry Restoration
- Roofing Replacement
- New Haven Elementary
- Masonry Restoration
- Eave trim replacement
- Palermo Elementary
- Masonry Restoration
- Lintel replacement