Cap Project Update: 6/1/25
Below is a message from Superintendent Dr. Runner on 6/1/25.
Dear MACS Family and Community, I wanted to share an update with you regarding the Capital Project work. Thank you for your flexibility with all of the construction! Dr. Runner, Superintendent
2024-2025 Capital Outlay Exception Project Mexico Middle School
- Installation of the conduit and wiring was run from the exterior of the building to the electrical panel on the second floor.
- Next Steps:
-
- Digital Display board will be delivered and installed.
- Solid surface sills and the cabinet for the nurse’s office will be fabricated and delivered.
-
2023 Capital Improvement Project
Mexico High School
For the replacement of the Air Handlers
- Construction of catwalk #1 building the framework and platform to the roof hatches
- Handrailing on the catwalk was constructed. (These handrailing’s are not finished.)
Mexico Middle School
- Contractors began removing the dirt off site at the Parent Drop Off area.
- Underground piping was delivered for the Middle School.
Next Steps
-
- Middle School
- Rough grading and storm structure installation
- Rear parking lot demolition and storm retention structures
- Middle School
-
- High School
- Finishing up the catwalk extension installation
- New Roof Hatch installation
- Condensate removal and replacement
- Attic HVAC replacement
- Masonry Restoration
- Window Replacement
- High School